Papillion Fire Station #2 - Building

Papillion Fire Station #2 - Building
           Place Order 

 

    

Contact:   Matt Veasman
PreBid Date:   08/08/2008 1000
PreBid Info:   A bidders conference has been scheduled for 11:00 a.m. on the 8th day of August, 2008 at the location of Papillion City Hall. All general contract and subcontract bidders are invited. Representatives of Architect will be in attendance.

Company:   Police Facility Design Group
Bid Date:   08/22/2008 1400
Bid Info:   Bids signed and under seal, excuted, and dated will be recieved at the office of the CITY OF PAPILLION, NEBRASKA by Jennifer Niemer, City Clerk, at Papillion City Hall 122 E. Third St., Papillion, NE 68046

Project Location:

Public Notes:
This project is the construction of a fire sub-station at 11749 S. 108th St, in Papillion, NE. The facility is approximately 13,000 sq. ft. in size.

Please return plans and specs to Upland Construction, 10910 J. Street, Omaha, NE 68137 for refund of Deposit.




Job Purchase Information:
Sets of Bidding Documents may be obtained from Drexel Technologies for a Refundable fee of $150.00 per set if plans and specs are returned to the Awarded General Contractor in good condition within 10 Days of bid opening. Make checks payable to the City of Papillion. Mail checks to: Drexel Technologies, Attn: Distribution, 10840 W 86th Street, Lenexa, KS 66214-1632. Bidding Documents will be shipped only if the requesting party assumes responsibility for all related shipping charges.


Addenda
  • 08/01/2008 - Addendum #1 Addendum #1 - Consists of 45 pages of 8 1/2 x 11  Click to View
  • 08/15/2008 - Addendum 2 Addendum #2 - Consists of 14 pages of 8 1/2 x11 and 1 11 x 17 Finish Legend  Click to View

The complete set of bid documents does not contain large format drawings.